MARCH 3, 2005
ITEM NO.: 1
FILE
NO.: S-867-SSSSS
NAME:
Chenal Valley Phase 25
(Lots 1 – 79 Block 83) Replat
LOCATION:
Located West of Chenal Parkway and North of Chenal Club Blvd.
DEVELOPER:
Chenal
Properties
#7
Valley Club Circle
Little
Rock, AR 72211
ENGINEER:
White-Daters
and Associates
#24
Rahling Circle
Little
Rock, AR 72223
AREA:
32.54 acres
NUMBER OF LOTS: 79
FT. NEW STREET: 4,300
CURRENT
ZONING: R-2,
Single-family
PLANNING
DISTRICT: 19 – Chenal Planning District
CENSUS
TRACT:
42.11
VARIANCES/WAIVERS
REQUESTED:
A variance to allow a five (5) foot side yard setback for Lots 2 –
12, 20 – 23, 31 – 32 and 40 – 79, Block 83 of the Chenal Valley Phase
26.
BACKGROUND:
On
June 22, 2001, a preliminary plat was approved for the proposed subdivision.
On October 7, 2004, the applicant proposed to replat the existing lots
to allow a reduced platted building line on a portion of the lots. The applicant indicated a fifteen (15) foot platted building
line for Lots 11 – 12 and 61 – 62 Block 83 of the Chenal Valley Phase 25
Subdivision. The applicant
indicated a twenty (20) foot building line for Lots 22 – 23, 32, 38 – 43,
55 - 56, 64 and 67 – 72 Block 83 of the Chenal Valley Phase 25 Subdivision
and the applicant requested a reduced rear yard setback of fifteen feet for
Lots 53 – 79 Block 83 of the Chenal Valley Phase 25 Subdivision.
The
development was proposed as a gated community with private streets.
There were seventy-nine (79) lots proposed and the site contained 32.54
acres. The applicant indicated
the average lot size as 75-feet by 130-feet or 9,750 square feet.
The proposed density was 2.42 units per acre.
Three
phases were proposed with Lots 1 – 12, 20 – 23, 31 – 32 and 40 – 79 in
the first phase. Lots 13 – 19
in the second phase and Lots 24 – 30 and 33 – 39 in the final phase.
The
area abutting Chenal Parkway was indicated as a dedicated tract to be
preserved as open space. The
applicant indicated a no vehicular access easement through the proposed tract.
A.
PROPOSAL/REQUEST:
The
applicant is now proposing to revise the previously approved plat to allow for
five-foot side yard setbacks within the proposed subdivision.
The developer of the project is requesting a variance to allow the
development of the subdivision similar to the “Oaks Development” across
Chenal Club Boulevard. The
developer is requesting the variances for a five-foot side yard setback for
Lots 2 – 12, 20 – 23, 31 – 32 and 40 – 79, Block 83 of the Chenal
Valley Phase 26 Subdivision.
B.
EXISTING CONDITIONS:
The
site was final platted in July 2004, and construction of new homes has begun.
The construction of a guardhouse, which is located at the entrance to
the subdivision, is also underway. The
Chenal Valley Country Club is located to the west of the site with the tennis
courts being located near the proposed residential lots.
The area abutting Chenal Parkway has been indicated as a dedicated
tract to be preserved as open space.
To
the south of the site, is a single-family subdivision (the Oaks at Chenal),
which has developed with reduced front, side and rear yard setbacks.
Chenal Parkway, a four-lane median divided roadway, is located to the
east of the site.
C.
NEIGHBORHOOD COMMENTS:
As of this writing, staff has not received any comment from area residents. The abutting property owners along with the Bayonne Place Property Owners Association, the Duquesne Place Property Owners Association and the Margeaux Property Owners Association were notified of the public hearing.
D.
ENGINEERING COMMENTS:
Public
Works Conditions: No comment on
the proposed revision to side yard setbacks.
E.
UTILITIES AND FIRE DEPARTMENT/COUNTY PLANNING:
Wastewater:
Sewer main extension required with easements if service is required for
the project. Contact the Little
Rock Wastewater Utility at 688-1414 for additional information.
Entergy:
No comment received.
Center-Point
Energy: Approved as submitted.
SBC:
No comment received.
Central
Arkansas Water: Easements are required as platted in
Instrument 2004-051912, Plat Book H, Page 4.
Contact Central Arkansas Water at 377-1225 for additional information.
Fire
Department: Place fire hydrants
per code. Contact the Little Rock
Fire Department at 918-3700 for additional information.
County
Planning: No comment.
CATA: No comment received.
F.
ISSUES/TECHNICAL/DESIGN:
Planning
Division: No
comment.
Landscape: No comment.
G.
SUBDIVISION COMMITTEE COMMENT:
(February 10, 2005)
Mr. Tim Daters of White-Daters and Associates was present representing the request. Staff stated the applicant had previously final platted the lots but was now requesting to amend the final plat to allow for reduced side yard setbacks. Staff noted there were no outstanding technical issues associated with the proposed request. There was no further discussion of the item. The Committee then forwarded the item to the full Commission for final action.
H.
ANALYSIS:
There
were no outstanding issues associated with the proposed request from the
February 10, 2005, Subdivision Committee meeting.
The applicant is proposing to revise the previously approved plat to
allow a five-foot side yard setback within the proposed subdivision.
Previous approvals allow for reduced setbacks on selected lots for the
fronts and rear yards. The
developer of the project is requesting a variance to allow the development of
the subdivision similar to the “Oaks Development” across Chenal Club
Boulevard. The effected lots
include Lots 2 – 12, 20 – 23, 31 – 32 and 40 – 79, Block 83 of the
Chenal Valley Phase 26 Subdivision.
The
developer has indicated a reduced side yard setback on these selected lots
would allow the subdivision to be developed in an alternating pattern and
allow for additional buildable area on these lots.
The developer has also indicated the concept of the subdivision is one
that allows for varying side yard setbacks which adds character to the
development. Staff is supportive
of this request. Staff does not
feel the reduced side yard setback will have an adverse impact on the
adjoining properties. To
staff’s knowledge there are no outstanding issues associated with the
proposed request.
I.
STAFF RECOMMENDATION:
Staff
recommends approval of the request subject to compliance with the conditions
outlined in paragraphs D, E and F of the above report.
Staff
recommends approval of the applicant’s request to allow a five-foot side
yard setback on the indicated lots.